N4 leg of toll plaza upgrade under way

By:  
Features Deputy Editor
 
The final phase of the R160-million toll plaza upgrade project being overseen by the N1/N4 freeway operator Bakwena Platinum Corridor Concessioniare started last month and is expected to be completed by October. Bakwena commercial manager Liam Clarke explains that this latest phase of a project aimed at improving traffic flow comprises the addition of two new lanes at the Marikana and Brits Toll plazas, one in each direction, and also necessitates the extension of the service tunnel and the toll canopy, the erection of two new booths, and associated electrical work.
 
 
 
 
 