COAL-TO-POWER
A draft environmental impact report (EIR) for the proposed construction of two loop-in- loop-out 400 kV power lines to connect the recently approved KiPower independent power producer (IPP) power plant to the Eskom grid was released on Friday for public comment by engineering and environmental consulting firm Jones & Wagener. The proposed 400 kV power lines would be constructed between the KiPower IPP power plant, south-east of Delmas, and a connection point on the Matla-Glockner 400 kV power line, about 12 km south-east of the N17 national road.