The Ity carbon-in-leach (CIL) gold project that Endeavour Mining’s in-house team is building in Côte d'Ivoire is tracking two months ahead of schedule and will pour its first gold at the beginning of the March 2019 quarter, rather than mid-year, the Canadian firm reported on Wednesday.
In a construction update, the company said that the project was about 75% completed. Nearly all the $412-million initial capital cost had been committed and about 65% had been spent.