Work is progressing well on the new 12,000 m³ reservoir and associated pipework on Namibia’s northern-most border with Angola. Progress is over 60% and completion is expected to be well in advance of the contractual completion date of 12 April 2018. The design and construction of the reservoir – awarded by the Namibia Water Corporation Ltd (NamWater) in October 2016 – is being conducted by a joint venture between B&K Civils and Windhoek-based Rock Leigh Investments.