Dalgaranga still tracking ahead of schedule

By:  
Creamer Media Senior Deputy Editor: Australasia
 
GOLD
The Dalgaranga gold project, in Western Australia, remains one month ahead of schedule, ASX-listed Gascoyne Resources told shareholders, with the project due to start gold production in May. Gascoyne told shareholders on Wednesday that process plant construction at Dalgaranga was 98% complete, with mining under way at the Golden Wings, Sly Fox and Gilbeys pits.
 
 
 
 
 