Despite heavy rains in the area over the last two weeks causing some delays, rare earths developer Northern Minerals MD George Bauk confirmed in a progress update on Monday that the Browns Range pilot plant project, in Western Australia, was on track for completion by the end of June. He said in a statement that turnkey solutions provider Primero Group continued to make steady progress on installation of structural steel and process plant modules, with electrical installation works having progressed and piping work having started.